Magnavale are excited that the progress of its Easton development is progressing rapidly. Since breaking ground in September 2022, the company has achieved significant milestones, positioning the development to become Europe’s most efficient cold store.
McClaren have completed the main concrete slab, and low bay cladding and steelwork for the staircase and office are now complete. Construction has also begun on the high bay automation, and the high bay cladding, which including the cranes, are currently being erected within the store’s steelwork lattice. The electrical infrastructure and fire suppression system are also making steady progress.
The refrigeration and oxygen reduction plantrooms, essential elements of the cold store, are under construction and nearing completion. Magnavale are pleased with the progress made so far and remains confident that they will complete construction in Q4 2024.
Magnavale’s new development in Easton, Grantham, is set to become the most efficient cold store in Europe, accommodating a capacity of 101,000 pallets. The fully automated cold store will operate solely on renewable energy, making it an environmentally sustainable solution for the modern cold storage industry.